The Gotthard Base Tunnel will remain closed for travel for months.

Published: Wednesday, Aug 16th 2023, 14:40

Mise à jour le : Vendredi, 13 octobre 2023, 14:12

Retour au fil d'actualité

The repair work in the Gotthard Base Tunnel is expected to take several months. Initial estimates of the damage have been exceeded, with 16 derailed and partially severely damaged freight cars still in the tunnel. Investigations have revealed that 8 kilometres of track and 20,000 concrete sleepers need to be replaced. This work is expected to take several months, with the SBB expecting both tunnel tubes to be fully operational again by early 2024. In the meantime, freight traffic is expected to resume on August 23rd, with passenger traffic continuing to be diverted via the panoramic route.nnnnnnnnnn









©Keystone/SDA

Articles connexes

Rester en contact

À noter

the swiss times
Une production de UltraSwiss AG, 6340 Baar, Suisse
Copyright © 2024 UltraSwiss AG 2024 Tous droits réservés